Busan Audit Committee Announces Results of Special Audit on Sasang–Hadan Line Construction Project

Apr 22, 2025 6  Views
◈ From October 21 to November 15, 2024, the Busan Audit Committee conducted a special audit of the “Sasang–Hadan Urban Railway Construction Project,” resulting in 10 administrative actions, 33 personnel-related measures, and a recommended cost reduction of KRW 1.159 billion.

◈ The sinkhole incident that occurred at 8:50 a.m. on September 21, 2024, at the starting point of Section 2 was found to be caused by multiple factors, including
▲heavy rainfall (379mm),
▲poor construction management during water-blocking and retaining wall work, and
▲improper drainage connection work.

◈ Additional findings included
▲inadequate performance by dedicated safety engineers,
▲improper reporting in the post-environmental impact assessment,
▲a lack of strict schedule management in line with revised project timelines, and
▲design changes including reductions in scope and cost due to construction and design flaws.
내용

The Busan Audit Committee (Chairperson: Yoon Hee-yeon) has announced the results of a special audit conducted on the Sasang–Hadan Urban Railway Construction Project between October 21 and November 15, 2024. The audit was launched in response to delays in project completionprolonged traffic congestion, and repeated sinkhole incidents that caused public concern over safety and inconvenience.



Key Findings

◈ The audit resulted in:

  • 10 administrative actions (2 corrections, 4 cautions, 4 notifications)

  • 33 personnel-related actions (11 advisories, 22 warnings)

  • KRW 1.159 billion in project cost reduction through design change recommendations

◈ The major sinkhole incident that occurred on September 21, 2024, in Zone 2 of the construction site was found to be caused by a combination of factors, including:

  • Heavy rainfall (379mm)

  • Inadequate water-blocking and retaining wall construction management

  • Improper drainage connections



Audit Observations

  • Poor Quality Control:
    A subcontractor without proper qualifications conducted water-blocking quality tests. These reports were accepted without verification, leading to groundwater inflow and soil loss during tunnel excavation.

  • Lack of Oversight:
    Busan Transportation Corporation instructed contractors to develop recovery plans for delayed schedules but failed to ensure their implementation or report issues to upper management.

  • Construction Deficiencies:

  • Weak retaining wall anchoring and missing structural piles

  • Improper drainage channel construction

  • Substandard soil blocking material permeability

  • Failure to update designs or supervise site adjustments

  • Environmental Oversight Failures:

  • Post-environmental impact reports reused old site photos

  • Soil contamination tests conducted at unauthorized locations

  • Reports submitted to Nakdong River Basin Environmental Office with inaccurate documentation



Actions Taken

  • Contractors and construction supervisors were notified of penalties.

  • Inaccurate cost estimations and redundant waterproofing materials led to KRW 893 million in recommended cost reductions.

  • Improper lump-sum pricing for electrical/mechanical tunnel components led to additional deductions for undelivered items.

  • The audit also pointed out deficient safety oversight, including role conflicts among safety engineers.



Chairperson Yoon Hee-yeon of the Audit Committee stated:

“This audit confirmed that the cause of the sinkhole was not only external factors like heavy rain, but also internal failures in quality control, safety management, and construction oversight. The findings will serve as a turning point to strengthen safety management systems and prevent similar incidents in the future.”